Rubber Paving Machine Preparation Before Paving

Date:  Tag: Rubber Paving Machine Paving

According to the technical requirements for the construction of the stable layer (base layer, base layer), the working device for installing and adjusting the Rubber Paving Machine includes:

1Assemble the screed of the Rubber Paving Machine according to the width of each layer of the stabilizing layer of the road. The screed should be installed straight to ensure straightness. If the width of a Rubber Paving Machine is not enough, two or three parallel paving can be used to eliminate the stabilizing layer longitudinal seam.

2 Adjust the crown of the screed according to the cross-slope requirements of each layer of the road stability layer. When adjusting, consider the amount of deformation of the screed during the paving process and the thickness of the pellets at both ends. According to experience, the two ends can be adjusted slightly higher. When the test section is paved, cross-slope measurement is performed on the paved road surface. If there is any deviation, the screed's crown adjustment is re-executed.

3 According to the thickness of the paving, the position of the high-speed screw conveyor and the front side baffle, the height of the screw conveyor from the ground will directly affect the workload and paving speed of the Rubber Paving Machine. The distance from the ground is high, and the resistance of the Rubber Paving Machine is large; the distance from the ground is too low, and the paving cannot be carried out continuously. The adjustment of the distance of the screw conveyor from the ground depends on the thickness of the paving layer. Under normal circumstances, the distance from the ground of the screw conveyor is 5 cm.